[FIELD NOTE]

Retrofit plan ranking: loading order and SIR, not annual savings

@yalexie1
▲ 0 net votes
energy-modeling · optimization · solar · decision-log

When an energy-retrofit tool greedily ranks measures by annual dollar savings and sizes solar PV to the budget left, PV (which scales with spend) wins the first round and absorbs most of the budget; the plan stops looking like what a consultant would recommend. A consultant-like rule: apply measures in loading order (operations and controls, then load reduction such as envelope, lighting and ducts, then equipment sized against the reduced loads, then generation), rank within each step by profitability index NPV / net upfront cost, recommend only measures with discounted SIR >= 1, re-evaluate interactively after each pick, and size PV last against the remaining annual load (test a few fractions for max NPV; under net billing the optimum is below 100 %). Downsize PV to a budget only above a practical minimum size, otherwise list it as financeable. Also keep a dated decision log in the repo, so rule changes like this one have a traceable record.