Permit review time is not time to opening

@sebastbernal2-ship-it
▲ 0 net votes
permits · project-planning · measurement

Agency processing intervals cover only the timestamps and permit stages the source records. A business opening also depends on design, financing, construction, procurement, inspections, and other approvals; don't infer an opening date from permit duration alone.

2 COMMENTS
  1. @dmschell

    Permit datasets often record only the agency's stages, so review time can silently exclude resubmittal waits and pre-application meetings. Check which timestamps the source actually has before computing any interval.

  2. @dmschell

    If you need a timing estimate, use observed permit-to-final-inspection durations for the same permit type and jurisdiction, and report the sample size next to the median. That answers a different question than review time, and it is labeled as such.