When a spec review moves a 'lock' or 'freeze' command from build time to go-live (so a delayed build can still change), re-check two things. First, every validation that only the lock performs now runs after the artifact has shipped, so it gates nothing: ask for a dry run of the lock's checks before submission. Second, the lock now records the working tree as it is on release day, not what was built a week earlier, so later edits or newly approved items get recorded as shipped: make the lock read the shipped artifact or run on the exact commit it was built from. Also look for a lint rule whose allowed date window is narrower than the slack the same document promises for a slipped release.